GreenRoc Mining Plc / EPIC: GROC / Market: AIM / Sector: Mining
6 July 2022
GreenRoc Mining plc
("GreenRoc" or the "Company")
Operational Update
Field Work Programme at TBS and Drilling Commenced at Amitsoq
GreenRoc Mining Plc (AIM: GROC), a company focused on the development of critical minerals projects in
Key Points
· Summer/autumn field work programme due to commence at TBS Q3 2022 with the objective of fast-tracking TBS to mine development
· Environmental Impact Assessment ("EIA") consultants, BioApp Greenland, to commence second year environmental baseline studies, providing the foundation for the development of an EIA
· Social Impact Assessment ("SIA") workshops to begin, managed by SIA consultants NIRAS A/S ('NIRAS')
· Assay results from the 249-hole 2021 drilling campaign at TBS are expected in early August
· It is hoped that the independent Competent Person's revised assessment of these drill results, which is expected to be completed by September, will support an enlarged Mineral Resource Estimate ("MRE") to build on the current Mineral Resource of 19Mt at 8.9% in-situ ilmenite
· International mining consultancy, SLR Consulting, has been engaged to undertake preliminary studies on mining methods and processing plant options for both TBS and Amitsoq
· The planned drilling programme has commenced at Amitsoq. It is expected to take around 12 weeks, targeting an upgrade and increase of the current Maiden JORC Resource of 8.28Mt at 19.75% Graphitic Carbon ("C(g)")
GreenRoc's CEO, Stefan Bernstein, commented:
"I am delighted to publish my first update to GreenRoc shareholders as the Company's CEO and to join the Company at such a key point in its development.
"We are excited to be kicking off the field season at TBS. After completing extensive drilling campaigns there in previous years, our focus for this field season is on collecting the other datasets which will be essential to the environmental and social impact assessments we have commissioned as part of the process for obtaining an exploitation licence.
"After a long wait, we are also approaching the finalisation of the laboratory testwork and revised resource assessment following last summer's drilling at TBS. We look forward to announcing the outcome on that front as soon as possible, which we are hopeful will lead to an upgraded mineral resource and provide the foundation for feasibility studies.
"Fast tracking TBS and our other flagship project, Amitsoq, towards development status is a key objective for the Company this year. Accordingly, alongside the progress at TBS I am delighted to confirm that our field team has now commenced phase two drilling at Amitsoq. Our objective by the end of this summer is for Amitsoq to join TBS in having had the bulk of exploration activities completed so that we can focus thereafter on completing the regulatory and scoping studies which will enable exploitation licences to be applied for at both assets."
Details
Having announced, in the Company's RNS of 4 April 2022, the appointment of BioApp Greenland ("BioApp") to undertake an Environmental Impact Assessment ("EIA") and NIRAS A/S ("NIRAS") to undertake a Social Impact Assessment ("SIA") at TBS, GreenRoc is pleased to provide further details of the field components of that forthcoming work.
GreenRoc has chartered a dedicated vessel for the coming field season, which will act as both a means of transport to and from TBS and as the base camp for the various field teams. The vessel is expected to arrive at TBS in the second half of July.
EIA Update
BioApp, a Danish/Greenlandic-based contractor and environmental expert with extensive operational experience in
At least two years of environmental baseline studies are required to be completed as part of an EIA. A first-year baseline study was carried out in the TBS area in 2018. The second-year baseline study will be carried out this summer. The fieldwork will be carried out by BioApp personnel with in-depth knowledge of the Project and its environs, and an extensive track record of environmental work acquired in the course of assisting on multiple projects in
Sampling will also include photo documentation of the seabed at the planned port location and in the vicinity of marine site sampling locations. Bergerhoff Gauges (which provide long term ambient dust data) will be deployed in each of the three resource areas, the southern, central and northern zones (see Figure 2), and a weather station will also be installed to provide site-specific weather data for the area.
This work is expected to commence in early August.
SIA Update
NIRAS, a Danish/Greenlandic multi-disciplinary engineering consultancy with extensive
Preparing and developing an SIA requires the collection and assessment of a wide range of relevant data from various sources, including baseline data on population and demographics, living and housing costs, nature and land use, social problems, income, industry, labour market, infrastructure, health, heritage, culture and language.
Collection of baseline data is made via desktop research, which will be supplemented by the involvement of local, regional and national stakeholders in
Archaeological Studies
GreenRoc has contracted the Greenlandic National Museum and Archives to conduct an archaeological survey over TBS. Large areas of
Mine Planning
The international mining consultancy, SLR Consulting, has been engaged to undertake preliminary studies on mining methods and processing plant options for both TBS and Amitsoq. These studies will feed directly into the EIA process and will also provide the foundations for future Scoping Studies and other technical development work.
MRE Assessment
Testwork results from the 2021 TBS drilling campaign are expected in early August. Once available, the independent Competent Person, IHC Mining, will be in a position to complete its revised assessment of the MRE for TBS, which is expected by September.
Amitsoq Island Phase 2 Drilling
GreenRoc is pleased to confirm that Phase 2 drilling has now commenced at the Amitsoq Island deposit. See the RNS dated 6 June 2022 for further details of the drilling programme.
This announcement contains inside information for the purposes of the
Forward Looking Statements
This announcement contains forward-looking statements relating to expected or anticipated future events and anticipated results that are forward-looking in nature and, as a result, are subject to certain risks and uncertainties, such as general economic, market and business conditions, competition for qualified staff, the regulatory process and actions, technical issues, new legislation, uncertainties resulting from potential delays or changes in plans, uncertainties resulting from working in a new political jurisdiction, uncertainties regarding the results of exploration, uncertainties regarding the timing and granting of prospecting rights, uncertainties regarding the timing and granting of regulatory and other third party consents and approvals, uncertainties regarding the Company's or any third party's ability to execute and implement future plans, and the occurrence of unexpected events.
Actual results achieved may vary from the information provided herein as a result of numerous known and unknown risks and uncertainties and other factors.
**ENDS**
For further information, please visit https://greenrocmining.com/ or contact:
GreenRoc Mining Plc Stefan Bernstein, CEO |
+44 20 3950 0724
|
|
|
Cairn Financial Advisers LLP (NOMAD) James Caithie / Sandy Jamieson / Louise O'Driscoll
|
+44 20 7213 0880 |
ETX Capital (Broker) Tom Curran / Thomas Smith |
+44 20 7392 1494
|
St Brides Partners (Financial PR & IR) Susie Geliher / Charlotte Page |
+44 20 7236 1177 |
|
|
About GreenRoc
GreenRoc Mining Plc is an AIM-quoted company which is developing mining projects in
Led by a group of highly experienced mining industry professionals with considerable knowledge of the Greenlandic mining sector, GreenRoc has a portfolio of 100% owned projects:
· Amitsoq Graphite, one of the highest-grade graphite deposits in the world with a combined Indicated and Inferred JORC Resource of 8.28 million tonnes (Mt) at an average grade of 19.75% giving a total graphite content of 1.63 Mt;
· Thule Black Sands Ilmenite ('TBS'), which has an initial Mineral Resource of 19Mt@ 43.6% Total Heavy Minerals with an in-situ ilmenite grade of 8.9%;
· Melville Bay Iron, which has a Mineral Resource Estimate of 67Mt at 31.4% iron and has been proven to be processable to a high-grade, 70% concentrate with low impurities; and
· Inglefield Multi-Element, which has the potential to host a range of mineralisation styles, including iron oxide-copper-gold.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.