13 June 2023
IOG plc
Blythe H2 First Gas
IOG plc ("IOG", or "the Company"), (AIM: IOG.L) confirms that First Gas has been safely delivered from the Blythe H2 well and provides an update on the planned near-term intervention.
Rupert Newall, CEO, commented:
"IOG's Drilling, Operations and Engineering teams have done an excellent job to bring the Blythe H2 well onstream within one week of our initial three-month guidance, despite losing over a month to the well control event. Strong collaboration with Petrofac (Well Operator), Shelf Drilling (rig contractor), ODEAM (infrastructure Duty Holder) and Perenco (terminal operator), among others, has enabled safe and efficient execution of this important well.
We are expediting equipment to the rig to resolve the apparent downhole mechanical blockage, which if successful could increase H2 flow rates by around month end to the 30-40 mmscf/d range that we guided pre-well. In addition, we continue to work very actively on next steps beyond H2 and expect to provide further updates shortly."
H2 First Gas
· First sales gas safely delivered from H2 into the Saturn Banks Reception Facilities and Bacton terminal on 12th June
· H2 brought onstream in three months and one week from spud date, versus initial guidance of approximately three months, despite 34 days lost to the well control event
o Hook-up and commissioning ("HUC") completed well ahead of schedule
· The well is in the ramp-up phase towards an expected initial maximum rate
o Maximum well test dry gas rate was 22.8 mmscf/d and 280-336 bbl/d condensate at the export pipeline pressure of 1250psi
Planned H2 intervention
· During testing, H2 flow appeared to be choked back below the levels indicated by reservoir properties by a downhole restriction
· Analysis of pressure and temperature data from the well test indicates a downhole restriction above the reservoir is choking back production
· Pressure build-up data since the test indicates reservoir permeability is in line with pre-drill expectations - further supporting the view that the issue is mechanical rather than reservoir driven
· Analysis of combined pressure and temperature data infers that a potential cause for the restriction may be a partially activated downhole valve
· H2 is intended to be flowed at initial rates until specialist downhole equipment arrives on the rig within the next two weeks to assess and, if necessary, manually actuate this valve
· This intervention would likely take up to a week at an estimated incremental cost net to IOG of c.
· If successful, the intervention would be expected to increase H2 flow rates to the previously guided 30-40 mmscf/d range
Production plan
· The H1 well was shut in as planned during the final H2 HUC. Post-intervention, the plan remains to produce initially from H2 only, to flush formation water out of the Saturn Banks Pipeline System and reduce associated opex
· No faults or fractures were encountered in the H2 reservoir section and no formation water was observed on testing
· Following a period of shut in to allow the water levels to re-equilibrate, the plan is to reopen H1 periodically at lower rates to flow gas and condensate with limited water production
Corporate and financial update
· The Company remains in discussions with an ad-hoc group of bondholders as stated on 7th June and will keep the market updated accordingly on progress
· Management continues to be fully focused on maximising production and managing costs very tightly
· Over June to date,
· While this recent increase is encouraging, significant volatility and uncertainty persist
· IOG also notes the
· The Company welcomes the introduction of EPL price floors, however expects the actual impact to be minimal given the particularly low gas floor and the requirement for both gas and oil floors to be met
· The change looks likely to favour larger integrated energy businesses with international production and LNG trading capabilities at a time when greater focus is needed on developing domestic low carbon gas supplies to displace higher carbon intensity LNG from overseas and improve security of supply
· The North Sea is a relatively mature basin and the
This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 as it forms part of
Enquiries:
IOG plc Rupert Newall (CEO) Dougie Scott (COO) James Chance (Head of Capital Markets & ESG)
|
+44 (0) 20 7036 1400 |
finnCap Ltd Christopher Raggett / Simon Hicks
|
+44 (0) 20 7220 0500 |
Peel Hunt LLP Richard Crichton / David McKeown |
+44 (0) 20 7418 8900 |
|
|
Vigo Consulting Patrick d'Ancona / Finlay Thomson
|
+44 (0) 20 7390 0230 |
About IOG:
IOG is a
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.