RNS Announcement
14 October 2024
AIM: SYN
Cambay Work Program Update
Synergia Energy Ltd ("Synergia" or the "Company") provides the following update regarding the Company's Cambay PSC joint venture and its carbon capture and storage ("CCS") projects in the
Cambay PSC
During the recent Technical Committee Meeting held by Synergia's JV partner, Selan Exploration Technology Limited ("Selan"), the planned work program associated with the Company's Cambay Field Production Sharing Contract ("Cambay PSC") in Gujarat State,
Well Number Completion Operation
C-70 Perforate MBS formation
C-63 Wellbore cleanout; re-perforate; install artificial lift pump
C-64 Install artificial lift pump
C-73 Wellbore cleanout; install artificial lift pump
C-20 Install artificial lift pump
C-74 Wellbore cleanout; install artificial lift pump
C-77H Well data acquisition; finalize future workover program
Selan plan to conduct workover operations on a minimum 3 wells and potentially up to 6 wells on the Cambay PSC.
The workover sequence, starting with C-70, will commence after the wells have been subjected to individual pressure gradient surveys during October / November 2024. All the contracts required for the workover operations are progressing as per the timeline. The Company believes the workover program will result in material incremental production and cashflow from the Cambay PSC and a better understanding of well behaviour ahead of the drilling of three new wells which is currently planned to commence Q2 2025. Synergia will be carried by Selan through the agreed
Medway Hub Camelot CCS project
Synergia is the nominated operator of
The Company is encouraged by the recent announcement of the
Cambay CCS Scheme
During July 2024, Synergia discussed its Cambay-based CCS scheme with the Directorate General of Hydrocarbons ("DGH") principals resulting in an agreement to develop and propose a proof of concept pilot project on the Cambay PSC. A recent meeting involving Synergia, DGH and Mumbai Institute of Technology personnel was held to progress the pilot project which the Company hopes will attract Government of
This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 as it forms part of
For and on behalf of Synergia Energy Limited
Roland Wessel
CEO
For further information, please contact:
Investor Enquires Synergia Energy Ltd Briana Stayt Investor Relations Email: bstayt@synergiaenergy.com Tel: +61 8 9485 3200 |
AIM Joint Broker Panmure Liberum Ltd Broker Mark Murphy / Rauf Munir / Freddie Wooding Tel: +44 (0)20 7886 2500 |
AIM Joint Broker Novum Securities Broker Colin Rowbury Email: crowbury@novumsecurities.com Tel: +44 20 7399 9427 |
AIM Nominated Adviser Strand Hanson Limited Nominated Adviser Ritchie Balmer / Rory Murphy Tel: +44 20 7409 3494 |
Media Enquires ( Vigo Consulting Investor Relations Patrick d'Ancona / Finlay Thomson Email: patrick.dancona@vigoconsulting.com finlay.thomson@vigoconsulting.com Tel:+ 44 20 7390 0230 |
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.