2024 Half Year Results
17 September 2024-
Management will host a webcast at 9:00 a.m.
Key updates:
l Akatara development project achieved mechanical completion in June 2024, with sales gas production commencing in July 2024 and reaching c.14mmscf/d. Production has been recently curtailed by a small mechanical issue in the gas processing facility's refrigeration compressors, with repairs underway. These repairs and their associated cost remain the responsibility of the EPCI contractor.
l Positive progress on the Montara oil storage tank repair and maintenance programme, which has allowed for the permanent stationing of shuttle tanker at the field to be discontinued in late-August, earlier than expected.
l Year-to date 2024 production (to end August 2024) has averaged c.17,500 boe/d, a c.42% increase year-on-year due to the success of both organic and acquisition driven growth over the period. Annual 2024 production guidance is reiterated at 18,500 - 21,000 boe/d, with an expected outcome towards the lower end of the range, given year-to-date production and ongoing Akatara activities.
l Operating expenditure guidance for 2024 is reiterated at
l Capital expenditure and other cash expenditure guidance is unchanged at
l
l Net debt of
Paul Blakeley, President and CEO commented:
"Increased production, coupled with robust price realisations and flat underlying operating costs, resulted in an improving financial performance in the first half of 2024, with adjusted EBITDAX and operating cash flows significantly higher year-on-year.
Our first half performance also benefited from the increasing diversification of the portfolio as we build greater reliability and resilience. The adverse weather which impacted our
Jadestone's primary focus so far in 2024 has been the completion and commissioning of the Akatara development project onshore
2024 FIRST HALF RESULTS SUMMARY
USD'000 except where indicated |
Six months ended 30 June 2024 |
Six months ended 30 June 2023 |
Twelve months ended 31 December 2023 |
|
|
|
|
Total hours worked lost time injury free (million) |
3.85 |
1.45 |
4.55 |
Total recordable injury rate |
3.12 |
0.00 |
0.86 |
Production, boe/day1 |
16,867 |
12,339 |
13,813 |
Realised oil price per barrel of oil equivalent (US$/boe)2 |
88.73 |
86.15 |
87.34 |
Realised gas price per thousand standard cubic feet (US$/mscf) |
1.64 |
1.41 |
1.53 |
Revenue3 |
185,060 |
86,660 |
309,200 |
Production costs |
(136,324) |
(90,650) |
(232,772) |
Adjusted unit operating costs per barrel of oil equivalent (US$/boe)4 |
31.72 |
40.27 |
37.24 |
Adjusted EBITDAX4 |
60,215 |
(3,127) |
90,647 |
Loss after tax |
(31,119) |
(59,934) |
(91,274) |
Loss per ordinary share: basic and diluted (US$) |
(0.06) |
(0.13) |
(0.18) |
Operating cash flows before movement in working capital |
27,946 |
(24,179) |
36,499 |
Capital expenditure |
47,618 |
23,807 |
115,882 |
Net (debt)/cash4 |
(69,131) |
7,782 |
(3,596) |
Operational and financial summary
l Zero lost time injuries in operated and non-operated assets. This involved working 3.85 million manhours in operated assets (H1 2023: 1.45 million manhours), an increase of 165% from H1 2023.
l Zero Tier 1 or Tier 2 process safety events, with a focus on pre commissioning activities at Akatara and ongoing asset integrity programs at operated assets.
l Production increased by 37% in H1 2024, reaching 16,867 boe/d, up from 12,339 boe/d in H1 2023. The increase was due to higher production from PenMal following the successful drilling campaign in late 2023, a higher working interest in the CWLH following completion of the acquisition of an additional 16.67% working interest in February 2024, full production from Sinphuhorm, acquired in February 2023, and a full period of production from Montara, compared to H1 2023 when production was shut in for much of the first quarter. These increases were partially offset by lower production at Stag compared to the prior period, impacted by extensive weather-related downtime in Q1 2024, a planned maintenance shutdown and underperformance of downhole pumps, which have required more frequent workovers than planned.
l Oil liftings totaled 2.2 mmbbls in H1 2024, more than double H1 2023 of 1.1 mmbbls, primarily driven by increased production described above and the addition of an underlift position at CWLH as part of the February 2024 acquisition, which subsequently formed part of a lifting in March 2024.
l The average oil price realisation, excluding the effect of hedging for H1 2024, was
l H1 2024 revenue totalled
l The CWLH 2 acquisition impacted revenues and production costs in H1 2024 by
l Production costs, excluding the movement in inventory and the under-lift impacts, decreased by 0.7%, from
l As at 30 June 2024, closing crude inventories totalled 442,781 bbls, and the Group had an underlift position of 270,449 bbls. After the H1 2024 reporting period, the Group generated
l Adjusted EBITDAX increased to
l Net loss after tax in H1 2024 of
l Operating cash flow before movements in working capital significantly improved in H1 2024 to
l Capital expenditure in H1 2024 of
l Net debt balance of
1 Production includes the Sinphuhorm Asset gas production in accordance with Petroleum Resource Management Systems guidelines, non-IFRS measures. However, in accordance with IAS 28 the investment is accounted for as an associated undertaking and only recognises the share of results of associate. Accordingly, the revenue and production costs from the Sinphuhorm Assets are excluded from the Group's financial results. Sinphuhorm production is included in the Group's production figures.
2 Realised oil price represents the actual selling price inclusive of premiums, excluding the effect of hedging.
3Revenue in H1 2024 and YE 2023 include hedging loss of
4 Adjusted unit operating costs per boe, adjusted EBITDAX and net (debt)/cash are non-IFRS measures and are explained in further detail on the Non-IFRS Measures section in this document.
For further information, please contact:
Jadestone Energy plc |
|
Paul Blakeley, President and CEO |
+65 6324 0359 ( |
Bert-Jaap Dijkstra, CFO Phil Corbett, Head of Investor Relations |
+44 (0) 7713 687467 ( |
|
|
|
|
Stifel Nicolaus Europe Limited (Nomad, Joint Broker) |
+44 (0) 20 7710 7600 ( |
Callum Stewart |
|
Jason Grossman |
|
Ashton Clanfield |
|
|
|
Peel Hunt LLP (Joint Broker) |
+44 (0) 20 7418 8900 ( |
Richard Crichton |
|
David McKeown Georgia Langoulant |
|
|
|
Camarco (Public Relations Advisor) |
+44 (0) 203 757 4980 ( |
Billy Clegg |
|
Georgia Edmonds Elfie Kent |
|
Webcast
The Company will host an investor and analyst presentation at 9:00 a.m. (BST) on Tuesday, 17 September 2024, including a question-and-answer session, accessible through the link below:
Webcast link: https://www.investis-live.com/jadestone-energy/66c5c57a7caa6c19003474c9/maert
Event title: Jadestone Energy plc first-half 2024 results
Time: 9:00 a.m. (BST)
Date: 17 September 2024
To join the presentation by phone, please use the below dial-in details from the
Global Dial-In Details: https://www.netroadshow.com/events/global-numbers?confId=70236
Access Code: 288973
ENVIRONMENT, SOCIAL AND GOVERNANCE ("ESG")
Jadestone is committed to being a responsible operator, that contributes to an orderly energy transition by helping to meet regional energy demand, whilst bringing positive social and economic benefits for its stakeholders, local communities and the people associated with its operations. Progress made during the half year ended 30 June 2024 is set out below across Jadestone's priority ESG areas.
HSE Governance
The Group continued its strong safety performance in the first year half of 2024 despite elevated levels of activity at the Akatara project. The Group reported no life altering events or significant impact to the environment, no regulatory enforcements notices, no Tier 1 or 2 process safety loss of primary containment events but one lost time injury (LTI). Jadestone's combined operations worked over 3.8 million manhours in H1 2024. The lost time injury related to staff sustaining a shoulder injury which required minor surgery.
Of note is the safety record at the Akatara gas development project site onshore
The Montara Venture FPSO tank inspection and repair program has been progressing well, following a Prohibition Notice issued by the regulator in June 2022. All tanks have been inspected and repairs are ongoing. Jadestone continues to engage closely and transparently with the regulator about the progress of the inspection and repair work and as each tank is completed, a Technical File Note is issued to the regulator which allows the tank to be released from the Prohibition Notice.
Net Zero interim targets
Jadestone's strategy for maximising reserves from existing producing oil and gas fields explicitly precludes frontier exploration and new greenfield development, a position that is in line with the IEA's Net Zero Emissions by 2050 Scenario. The Group is well positioned to remain relevant in the face of energy transition as a responsible steward of mid-life assets divested by larger companies, committed to upholding climate targets and executing its Net Zero by 2040 pledge.
The Company is committed to reduce Scope 1 and 2 absolute GHG emissions from its operated assets by 20% by 2026 and by 45% by 2030 (from 2021 levels) on its pathway to Net Zero by 2040. These interim targets will be achieved through a combination of measures, including minimising flaring, methane quantification, monitoring and reduction as well as reliance on carbon credits within the regulatory schemes of Jadestone's operating regions. For details of Jadestone's Net Zero GHG reduction plan, please refer to the 2023 Sustainability Report.
Group's H1 2024 Scope 1 GHG emissions1 during H1 2024 were slightly below plan, due to operations at Stag being affected by monsoon activity and flaring reduction initiatives at Montara. At the Montara site, a 33% reduction on flaring emissions compared to workplan and budget was achieved in H1 2024, due to a heightened focus on minimisation of flaring during normal production as part of a three-step flare optimisation plan for Montara. This plan involves:
1 Includes Montara, Stag and PenMal sites; Jadestone will integrate GHG emissions from the Akatara Gas field operations in the Full Year 2024 report.
· Reinjection compressor ("RIC") control logic modifications and automation of the injection choke, with the scope completed in May 2024, resulting in historically low flare rates post completion;
· Continued focus on reliability of the RIC resulting in significant improvement in RIC uptime during H1 2024;
· Feasibility analysis into increasing the capacity of the RIC. The engineering studies have commenced and will be completed during H2 2024.
These initiatives are an important cornerstone of Jadestone's Net Zero implementation roadmap to 2030.
The Company continues to build a fit-for-purpose Leak Detection and Repair programme across all operated assets and targets the introduction of annual leak detection and repair ("LDAR") at each operated site by the end of 20241.
Governance
Jadestone's Board underwent a number of changes during the first quarter of 2024, with the longer-term objective to ensure that the Board is sized appropriate to the Company's scale and ambition, while maintaining the right capabilities and adhering to corporate governance standards.
On 25 January 2024, the Company announced the appointment of Joanne Williams as an independent non-executive director. Ms. Williams is the Chair of both the HSEC Committee and the Montara Technical Committee, and a member of the Audit Committee and the Disclosure Committee.
On 25 March 2024, the Company announced the appointment of Adel Chaouch as an independent non-executive director. On the same day, the Company announced the resignation of Lisa Stewart as an independent non-executive director and Robert Lambert as an independent non-executive director.
On 27 March 2024, the Company announced the resignation of Dennis McShane as an independent non-executive director and Chair of the Board. On the same day, the Company announced the election of Adel Chaouch as the Chairman of the Board. Mr. Chaouch is the Chairman of the Governance and Nomination Committee, and a member of the Remuneration Committee.
On 9 May 2024, the Company announced the appointment of Linda Beal as an independent non-executive director. Ms. Beal is the Chair of the Audit Committee, replacing Iain McLaren who, in line with previous announcements, did not seek re-election at the Company's Annual General Meeting and formally stepped down on 13 June 2024. Ms. Beal is a member the Governance and Nomination Committee and the Remuneration Committee.
Effective 12 June 2024, Joanne Williams and David Neuhauser joined the CEO and CFO on the Disclosure Committee.
On 3 July 2024, the Company announced that Bert-Jaap Dijkstra, Executive Director and Chief Financial Officer ("CFO"), has decided to leave the Company. Mr. Dijkstra will remain in his post during the publication of the Company's 2024 Half-Year Results and support the October 2024 redetermination of the Company's reserve-based lending facility.
The Company is currently making good progress on both appointing a replacement CFO and the ongoing search for a Chief Operating Officer.
1 With an exception of Lemang, which will have an LDAR exercise implemented within 12 months of starting operations.
Producing assets
Montara Project (100% working interest, operator)
The Montara fields averaged 4,951 bbls/d in H1 2024, compared to 2,931 bbls/d in H1 2023. The year-on-year increase is primarily explained by Montara production being shut in during the start of 2023 until late March 2023 for repairs and maintenance activity on the Montara Venture FPSO's storage tanks.
Production during the first half of 2024 was impacted by the cyclone season early in the year, and the temporary shut in of the H6 and Swift-2 wells pending repairs. Both wells were brought back online early in the second half of 2024.
The Montara Venture FPSO tank inspection and repair programme is progressing well, resulting in increased oil storage capacity. This has allowed for the shuttle tanker operation, which had been in place to provide operational flexibility for Montara during the repair programme, to cease in late August 2024, earlier than planned.
The Group is progressing its plans to re-drill the Skua-11 well. This well is expected to boost Montara production through reinstating production from the Skua-11 well and is also targeting additional reserves in the Skua structure.
In total, three cargoes totalling c.0.8 mmbbls (H1 2023: one cargo of c.0.3 mmbbls) were lifted from Montara in the first half of 2024, with an average oil price realisation of
CWLH (33.33% working interest)
On 14 February 2024, the Group completed the acquisition of an additional 16.67% working interest in the Cossack, Wanaea, Lambert and Hermes oil fields ("CWLH") offshore western
During the first half of 2024, Jadestone's net production from the CWLH fields averaged 2,951 bbls/d, compared to 1,569 bbls/d in H1 2023. The year-on-year change is primarily explained by the increase in the Group's working interest referenced above.
Following engagement with the CWLH joint venture, total abandonment trust fund payments associated with the acquisition of the additional 16.67% interest completed in early 2024 have been revised down to
The Group lifted one cargo of c.0.7 mmbbls in the first half for an average oil price realisation of
Stag (100% working interest, operator)
The Stag field averaged 1,921 bbls/d in the first half of 2024, compared to 2,879 bbls/d in H1 2023. The first half of 2023 benefited from the onset of production of the Stag-50H and 51H wells drilled in late 2022. Stag field production in H1 2024 reflected greater than normal weather-related downtime in Q1 2024, a planned maintenance shutdown and mechanical issues in several wells which required workovers.
The Group continues to review options for further infill wells on the Stag field.
The Group sold one c.0.2 mmbbls cargo (H1 2023: two cargoes totalling c.0.5 mmbbls) of Stag crude in the first half of 2024. Premiums for Stag crude have remained robust, with the H1 2024 cargo being sold at
PM323 PSC (60% working interest, operator)
The PM323 PSC produced an average of 3,839 bbls/d net to Jadestone's working interest in H1 2024 (H1 2023: 1,667 bbls/d). The year-on-year increase is a result of the positive impact of the Group's infill drilling programme on the East Belumut field in late-2023.
The Group is progressing plans for further infill drilling on the East Belumut field, in particular focusing on the undrained southwestern area of the field discovered during the 2023 campaign.
A total of c.0.4 mmbbls (H1 2023: 0.1mmbbls) were lifted from the PM323 PSC in the first half of 2024, with an average oil price realisation of
PM329 PSC (70% working interest, operator)
The PM329 PSC produced an average of 1,616 boe/d net to Jadestone's working interest in H1 2024, consisting of 1,103 bbls/d of oil and 3.1 mmscf/d of gas (H1 2023: 2,212 boe/d, consisting of 1,518 bbls/d of oil and 4.2 mmscf/d of gas). The year-on-year decrease is primarily explained by natural decline.
A total of c.0.1 mmbbls (H1 2023: 0.2mmbbls) of oil were lifted from the PM323 PSC in the first half of 2024, with an average oil price realisation of
SFA Cluster (100% working interest, operator)
In July 2024, Jadestone was awarded a 100% participating interest in a Small Field Asset Production Sharing Contract (the "SFA Cluster PSC") offshore Peninsular Malaysia. The SFA Cluster PSC covers an area of 348km2 in shallow water offshore Peninsular Malaysia located adjacent to the Group's existing operated PM323 and PM329 PSCs, and is surrounded by the PM428. The SFA Cluster PSC contains the Penara, Puteri-Padang and North Lukut fields, assets in which Jadestone initially acquired a non-operated interest at the time of the Group's entry into
Jadestone currently estimates that the SFA Cluster PSC contains c.15 mmbbls of gross 2C contingent resources. Leveraging the experience gained through the successful 2023 infill drilling campaign on the PM323 licence, Jadestone believes there is the potential for significant upside from future infill drilling across the existing SFA Cluster fields, as well as opportunities on the surrounding PM428 PSC. The Group intends to continue its technical assessment of the SFA Cluster prior to submission of a field development and abandonment plan to PETRONAS.
PM428 PSC (60% working interest, operator)
In January 2024, Jadestone was awarded a 60% operated interest in the PM428 PSC offshore Peninsular Malaysia. The PM428 PSC is adjacent to the PM323 and PM329 PSCs, and surrounds the SFA Cluster PSC (referenced above). The PM428 PSC carries a
Akatara gas development (100% working interest[1], operator)
The Akatara gas development is located within the Lemang Production Sharing Contract onshore
Development activity at Akatara peaked in the first half of 2024. The focus during the period was on completing the installation of equipment and infrastructure at Akatara Gas Processing Facility ("AGPF"), tying in the development wells, facilities and flowline, followed by pre-commissioning, commissioning and start-up activities.
The workover campaign on the five existing Akatara wells, which provide gas to the AGPF, was successfully completed during the period, with the five wells flowing at an aggregate rate of 54 mmscf/d, significantly in excess of the c.25 mmscf/d of raw feed gas required under the gas sales agreement. In addition, the 8" diameter 17km pipeline exporting gas from the AGPF was successfully tested and tied into the regional gas trunkline.
A major milestone was reached on 22 June 2024 with declaration of Mechanical Completion at the AGPF and the introduction of reservoir gas from one of the five production wells, with condensate production also commencing at this point.
Commissioning of the facility continued into the second half of 2024, with commercial gas sales commencing on 31 July at a rate of c.4 mmscf/d, along with LPG production. During August, commercial gas sales reached c.14 mmscf/d, with production recently curtailed due to mechanical issues with the facility's refrigeration compressors, where repairs are currently underway.
Sinphuhorm (9.52% working interest, non-operated)
During the first half of 2024, the Sinphuhorm field produced an average of 1,585 boe/d (1,565 boe/d gas and 23 bbls/d of condensate). Production for the period 23 February 2023 (when Jadestone completed the acquisition of its Sinphuhorm interest) to 30 June 2023 averaged 1,531 boe/d, or 1,083 boe/d averaged over the first half of 2023.
Activity at the field during the first half of 2024 mainly comprised a booster compression project, which aims to sustain plateau production levels over the remaining life of the concession. The booster compression project was completed at the end of May 2024.
As this is an investment in associate, the Group does not recognise its share of revenues and production costs, instead recognising its share of results of associate. Dividends of
Pre-production assets
Block 51 (100% working interest, operator) and Block 46/07 (100% working interest, operator) PSCs
In January 2024, the Group announced that it had signed a Heads of Agreement ("HoA") with PetroVietnam Gas Joint Stock Corporation for the Gas Sales and Purchase Agreement ("GSPA") relating to the Nam Du and U Minh ("NDUM") gas fields development, located in the Block 46/07 and Block 51 Production Sharing Contracts in shallow water offshore southwest
Following signature of the HoA, the Group commenced detailed negotiations over a fully termed GSPA, which are currently ongoing. The GSPA is also a precursor to the submission of an updated Field Development Plan for the Nam Du and U Minh fields, the approval of which is required before a Final Investment Decision can be taken. The Group is currently updating this FDP, which will specify the development concept for the NDUM fields, associated capital and operating cost estimates, and a schedule to first gas.
The Block 46/07 PSC includes a commitment to drill an exploration well. This commitment has been extended several times from 2015 up to the end of June 2024. Historically, extension requests have been approved after expiry. An extension request was filed by the Company in February 2024 and is consistent with previous successful extensions, in that Jadestone proposes to drill this well as part of the development drilling for the Nam Du field development project.
The Tho Chu discovery in Block 51 was under a suspended development area status. The Group is working with Petrovietnam and other government entities to obtain a suspension of the relinquishment obligation for Block 51.
FINANCIAL REVIEW
The following table provides selected financial information of the Group, which was derived from, and should be read in conjunction with, the unaudited condensed consolidated interim financial statements for the period ended 30 June 2024.
USD'000 except where indicated |
Six months ended 30 June 2024 |
Six months ended 30 June 2023 |
Twelve months ended 31 December 2023 |
|
|
|
|
Production, boe/day1 |
16,867 |
12,339 |
13,813 |
Sales volume, barrels of oil equivalent (boe) |
2,330,574 |
1,119,011 |
3,862,741 |
Realised oil price per barrel of oil equivalent (US$/boe)2 |
88.73 |
86.15 |
87.34 |
Gas sales, thousand standard cubic feet (mscf) |
559,888 |
752,660 |
1,366,505 |
Realised gas price per thousand standard cubic feet (US$/mscf) |
1.64 |
1.41 |
1.53 |
Revenue3 |
185,060 |
86,660 |
309,200 |
Production costs |
(136,324) |
(90,650) |
(232,772) |
Adjusted unit operating costs per barrel of oil equivalent (US$/boe)4 |
31.72 |
40.27 |
37.24 |
Adjusted EBITDAX4 |
60,215 |
(3,127) |
90,647 |
Unit depletion, depreciation & amortisation (US$/boe) |
13.02 |
13.15 |
14.14 |
Impairment of assets |
- |
- |
(29,681) |
Loss before tax |
(29,129) |
(70,275) |
(102,766) |
Loss after tax |
(31,119) |
(59,934) |
(91,274) |
Loss per ordinary share: basic and diluted (US$) |
(0.06) |
(0.13) |
(0.18) |
Operating cash flows before movement in working capital |
27,946 |
(24,179) |
36,499 |
Capital expenditure |
47,618 |
23,807 |
115,882 |
Net (debt)/cash4 |
(69,131) |
7,782 |
(3,596) |
Benchmark commodity price and realised price
l The average oil price realisation, excluding the effect of hedging increased in H1 2024 by 3.0% to
1 Production includes the Sinphuhorm Asset gas production in accordance with Petroleum Resource Management Systems guidelines, non-IFRS measures. However, in accordance with IAS 28 the investment is accounted for as an associated undertaking and only recognises dividends received. Accordingly, the revenue and production costs from the Sinphuhorm Assets are excluded from the Group's financial results. Sinphuhorm production is included in the Group's production figures.
2 Realised oil price represents the actual selling price inclusive of premiums, excluding the effect from hedging.
3 Revenue in H1 2024 and YE 2023 includes a hedging charge of
4 Adjusted unit operating cost per boe, adjusted EBITDAX and net (debt)/cash are non-IFRS measures and are explained in further detail on the Non-IFRS Measures section in this document.
Production and liftings
The average production recorded a 37% growth for H1 2024 with 16,867 boe/d compared to 12,339 boe/d in H1 2023. The overall increase of 4,528 boe/d was the result of the following factors:
· Montara's production rose by 2,020 bbl/d, reflecting the phased restart that began in March 2023, which impacted H1 2023 output. In contrast, H1 2024 benefited from a full six months of production.
· PenMal added 1,576 bbl/d following the successful PM323 infill drilling in late 2023, partially offset with natural field decrease at PM329.
· CWLH's production increased by 1,382 bbl/d following the completion of a second acquisition in February 2024, which doubled the working interest in the assets.
· Sinphuhorm contributed an additional 508 boe/d in H1 2024, benefiting from a full six months of production compared to H1 2023, when the asset was acquired in February 2023; and
The above increase was partly offset by:
· Stag decreased 958 bbls/d due to extended downtime caused by adverse weather conditions and increased workover activity due to mechanical issues in several wells which required workovers.
Lifted oil volumes were higher in H1 2024 compared to H1 2023 predominately due to:-
In mmbbls except where indicated |
Six months ended 30 June 2024 |
|
Six months ended 30 June 2023 |
Remark |
CWLH |
0.7 |
|
- |
One lifting immediately following the completion of second acquisition. |
Montara |
0.8 |
|
0.3 |
H1 2024 3 liftings vs H1 2023 1 lifting with phased production resumed in late March 2023. |
Stag |
0.2 |
|
0.5 |
One lifting in H1 2024 compared to two liftings in H1 2023. |
PenMal |
0.5 |
|
0.3 |
Successful drilling campaign led to higher production available for lifting nomination. |
|
|
|
|
|
Total |
2.2 |
|
1.1 |
H1 2024 10 liftings vs H1 2023 6 liftings. |
|
|
|
|
|
PenMal gas sales (mmscf) |
559.9 |
|
752.7 |
Decrease in gas sales driven by natural decline at PM329 asset. |
|
|
|
|
|
Revenue
The Group generated gross revenues before hedging results of
A commodity swap hedge resulted in a charge of
The period-on-period increase in total net revenues of
· Higher lifted volumes, which resulted in an increase of
· Increased average oil price realisation, excluding the effect of hedging of
· Lower gas sales with reduced average gas price realisation of
· Hedging resulted in a loss of
Production costs
Production costs in H1 2024 totalled
|
|
H1 2024 USD'000 |
|
H1 2023 USD'000 |
|
Variance USD'000 |
|
Note |
|
|
|
|
|
|
|
|
|
Operating costs |
|
53,693 |
|
52,562 |
|
1,131 |
|
(i) |
Workovers |
|
10,633 |
|
9,531 |
|
1,102 |
|
(ii) |
Logistics |
|
13,956 |
|
14,743 |
|
(787) |
|
(iii) |
Repairs and maintenance |
|
28,090 |
|
28,378 |
|
(288) |
|
(iv) |
Tariffs and transportation costs |
|
3,656 |
|
3,035 |
|
621 |
|
(v) |
Supplementary payments and royalties |
|
6,324 |
|
7,298 |
( |
(974) |
|
(vi) |
Underlift, overlift and crude inventories movement |
|
19,972 |
|
(24,897) |
|
44,869 |
|
(vii) |
|
|
136,324 |
|
90,650 |
|
45,674 |
|
|
(i) Operating cost rose by
- CWLH operating costs increased by
- Stag shuttle tanker charter rates reduced by
- Montara's operating costs decreased by
- PenMal operating costs increase by
(ii) Workover costs increased by
(iii) Logistics costs reduced by
(iv) Repair and maintenance ("R&M") reduced
(v) Tariffs and transportation increased by
(vi) Supplementary payment and royalties decreased
(vii) Underlift, overlift, and crude inventory movements increased by
Adjusted unit operating cost per boe was
Depletion, depreciation and amortisation ("DD&A")
Depletion charges for oil and gas properties increased by 73.4% to
Depreciation of the Group's right-of-use assets and plant and equipment increased to
Other expenses
Other expenses increased
Finance costs
Finance costs in H1 2024 were
· A warrant reserve was established during the 2023 equity raise, resulting in a
· Lending fees decreased
1The term "Saudi CP" typically refers to the Saudi Contract Price (CP), which is a benchmark price for liquefied petroleum gas (LPG) in the global market.
· The RBL accretion fees and interest expenses increased by
· ARO accretion expense increased by
Other financial gains
Other financial gains in H1 2024 amounted to
Taxation
The tax expense of
The tax charge on the Group's loss differs from the amount that would arise using the standard rate of income tax applicable in the countries of operation as explained below:
|
|
H1 2024 USD'000 |
|
H1 2023 USD'000 |
|
|
|
|
|
|
|
Loss before tax |
|
(29,129) |
|
(70,275) |
|
|
|
|
|
|
|
Tax calculated at the domestic rates appliable to the profit/loss in the respective countries ( |
|
(4,646) |
|
(18,100) |
|
|
|
|
|
|
|
Less the effects of: |
|
|
|
|
|
Australian Petroleum Resource Rent Tax (PRRT) credit |
|
(5,741) |
|
(231) |
( |
Deferred PRRT tax expense |
|
545 |
|
- |
|
Non-deductible expenses |
|
1,787 |
|
5,191 |
|
Deferred tax assets not recognised |
|
7,856 |
|
4,977 |
|
Other income not subjected to tax |
|
(482) |
|
- |
|
Adjustments to prior year |
|
2,671 |
|
(2,178) |
|
|
|
|
|
|
|
Tax expense/(credit) for the period |
|
1,990 |
|
(10,341) |
|
|
|
|
|
|
|
RECONCILIATION OF CASH
US |