Commencement of Akatara Contractual Gas Sales
31 July 2024 -
Since 22 June 2024, when the Company announced mechanical completion of the Akatara Gas Processing Facility (the "Facility") and the introduction of reservoir gas into the Facility, raw gas production has ranged between 3-8 mmscfd, allowing for commissioning of the Facility's systems and the start of condensate production, which has totalled c.4,700 bbls to date.
On 31 July 2024, following successful packing of the 17km export pipeline from the Akatara field, commercial gas sales into the regional trunkline in
Jadestone will issue a further announcement once full DCQ (c.20 mmscfd) sales gas production is achieved, which is expected within the next two weeks.
Paul Blakeley, President and CEO commented:
"The Akatara project has now met the key major milestone of first contractual gas sales, just over two years since the original investment decision was made and just five weeks after introducing reservoir gas into the processing facility. Successfully commissioning a major new processing plant, producing gas, condensate and LPGs in a relatively remote location in
On behalf of our shareholders, I want to thank all of the Jadestone employees and our contractors who have worked around the clock over the past months to address the challenges and issues that are entirely normal when commissioning a facility of this nature. The work doesn't stop there, as we will be laser focused on refining the processes and procedures at the Akatara processing plant to deliver the highest levels of uptime.
This is a major milestone for our company, a new low-cost production base in
-ends-
For further information, please contact:
Jadestone Energy plc |
|
Paul Blakeley, President and CEO |
+65 6324 0359 ( |
Bert-Jaap Dijkstra, CFO Phil Corbett, Head of Investor Relations |
+44 (0) 7713 687467 ( |
|
|
|
|
Stifel Nicolaus Europe Limited (Nomad, Joint Broker) |
+44 (0) 20 7710 7600 ( |
Callum Stewart |
|
Jason Grossman |
|
Ashton Clanfield |
|
|
|
Peel Hunt LLP (Joint Broker) |
+44 (0) 20 7418 8900 ( |
Richard Crichton |
|
David McKeown Georgia Langoulant |
|
|
|
Camarco (Public Relations Advisor) |
+44 (0) 203 757 4980 ( |
Billy Clegg |
|
Andrew Turner Elfie Kent |
|
About Jadestone Energy
Jadestone Energy plc is an independent upstream company focused on the
Led by an experienced management team with a track record of delivery, who were core to the successful growth of Talisman Energy's business in
Jadestone is a responsible operator and well positioned for the energy transition through its increasing gas production, by maximising recovery from existing brownfield developments and through its Net Zero pledge on Scope 1 & 2 GHG emissions from operated assets by 2040. This strategy is aligned with the IEA Net Zero by 2050 scenario, which stresses the necessity of continued investment in existing upstream assets to avoid an energy crisis and meet demand for oil and gas through the energy transition.
Jadestone Energy plc (LEI: 21380076GWJ8XDYKVQ37) is listed on the AIM market of the London Stock Exchange (AIM: JSE). The Company is headquartered in
The information contained within this announcement is considered to be inside information prior to its release, as defined in Article 7 of the Market Abuse Regulation No. 596/2014 which is part of
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.