Akatara Update
19 August 2024 -
As previously reported, gas sales from the Akatara field commenced on 31 July 2024 at an initial rate of c.4 mmscfd. Since then, the gas plant has been progressively made operational and raw gas production into the Akatara Gas Processing Facility ("AGPF") has been steadily increased to 20 mmscfd, resulting in current gas sales in the range of 11-14 mmscfd.
The AGPF's export compressors, which pressurise the sales gas for export into the regional gas transportation pipeline system, require further commissioning work, which will allow the plant to achieve the full raw gas volume of c.25mmscfd and deliver the sales gas daily contract quantity ("DCQ") of c.20 mmscfd, as specified in the Akatara gas sales agreement. This activity is expected to complete this month, with any associated costs remaining the responsibility of the main contractor and equipment vendor.
Paul Blakeley, President and CEO commented:
"We continue to make good progress at the Akatara project towards final completion of the full processing facility, with recent tests demonstrating that well delivery is strong and that the facilities can handle the required raw gas volumes. Final completion, and plant handover to Jadestone, will occur after an extended production test at DCQ volumes, which is a contractual condition. We are confident this will be achieved once the export compressors are fully operational at design pressures."
-ends-
For further information, please contact:
Jadestone Energy plc |
|
Paul Blakeley, President and CEO |
+65 6324 0359 ( |
Bert-Jaap Dijkstra, CFO Phil Corbett, Head of Investor Relations |
+44 (0) 7713 687467 ( |
|
|
|
|
Stifel Nicolaus Europe Limited (Nomad, Joint Broker) |
+44 (0) 20 7710 7600 ( |
Callum Stewart |
|
Jason Grossman |
|
Ashton Clanfield |
|
|
|
Peel Hunt LLP (Joint Broker) |
+44 (0) 20 7418 8900 ( |
Richard Crichton |
|
David McKeown Georgia Langoulant |
|
|
|
Camarco (Public Relations Advisor) |
+44 (0) 203 757 4980 ( |
Billy Clegg |
|
Andrew Turner Elfie Kent |
|
About Jadestone Energy
Jadestone Energy plc is an independent upstream company focused on the
Led by an experienced management team with a track record of delivery, who were core to the successful growth of Talisman Energy's business in
Jadestone is a responsible operator and well positioned for the energy transition through its increasing gas production, by maximising recovery from existing brownfield developments and through its Net Zero pledge on Scope 1 & 2 GHG emissions from operated assets by 2040. This strategy is aligned with the IEA Net Zero by 2050 scenario, which stresses the necessity of continued investment in existing upstream assets to avoid an energy crisis and meet demand for oil and gas through the energy transition.
Jadestone Energy plc (LEI: 21380076GWJ8XDYKVQ37) is listed on the AIM market of the London Stock Exchange (AIM: JSE). The Company is headquartered in
This release does not include inside information.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.