Keras Resources plc ('Keras' or the 'Company')
Operations Update - Diamond Creek Phosphate Project,
Keras Resources plc (AIM: KRS) is pleased to provide an update on operations from its high-grade Diamond Creek organic rock phosphate mine ("Diamond Creek') and wholly owned
· The 2024 mining campaign is now underway and will run through till end November 2024; and
· The Delta Facility is currently operating at full capacity, on a single shift basis.
The Diamond Creek mining campaign is now underway, starting later than usual due to focus on the Delta Facility construction, commissioning and production ramp-up. The 2024 campaign plans for production of between 6,000 and 8,000 tons of which 3,000 tons to date has already been mined and hauled down to the laydown area at Diamond Creek. Crushed run-of-mine ("ROM") ore will progressively be hauled to the Delta Facility prior to the onset of winter snowfall for milling to 10 mesh and 50 mesh for direct sales as well as feed for the recently commissioned granulator plant to produce 240SGN PhoSul® with the Company's Phosul Utah LLC joint venture ("JV") partners. This will be the first winter that all ROM is stored in a dry, under-roof environment which will significantly benefit the beneficiation process.
Since commissioning the Delta Facility, additional minor plant modifications have continued to improve both consistent overall production and product quality and is now running at full capacity allowing the JV to now market PhoSul® granulates into the autumn planting season.
Graham Stacey, CEO of Keras commented, "Ramping up of our Delta Facility to full capacity is the next milestone achieved by the team in
"The continuation of mining at Diamond Creek during the 2024 summer season to generate ore for both in-house sales as well as feed to the PhoSul Utah JV has progressed well to date and will continue through to end-November which will set us up for beneficiation and sales in
The Delta Facility has brought the business stability we've been looking for since acquiring 100% in Falcon Isle which we will continue to build on with both Falcon Isle products and PhoSul Utah JV granulate sales."
The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under Article 7 of the Market Abuse Regulation (EU) No. 596/2014 (as amended) as it forms part of the domestic law of the
**ENDS**
For further information please visit www.kerasplc.com, follow us on Twitter @kerasplc or contact the following:
Graham Stacey
|
Keras Resources plc |
info@kerasplc.com
|
Nominated Adviser & Joint Broker Ewan Leggat / Caroline Rowe
Joint Broker Damon Heath / Erik Woolgar
|
SP Angel Corporate Finance LLP
Shard Capital Partners LLP
|
+44 (0) 20 3470 0470
+44 (0) 207 186 9900
|
Notes:
Keras Resources (AIM: KRS) wholly owns the Diamond Creek organic phosphate mine in
The Company is focused on continuing to build market share in the fast-growing US organic fertiliser market and build Diamond Creek into the premier organic phosphate producer in the US .
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.