10 July 2023
Scotgold Resources Limited ("Scotgold", the "Company" or the "Group")
Production, Sales, and Operations Update - Q2 2023 and H1 2023
Scotgold Resources Limited (AIM: SGZ),
Operational and Production Review
On 19 January 2023, the Company outlined its 2023 mine operations plan. This plan was based on its then current grade control model and included limited resource definition drilling information undertaken in 2022. Central to the 2023 mine operations plan was the transition to long hole open stoping ('LHS').
As announced on 27 March 2023, the 430 West Ore drive development was halted in late February due to declining gold grades. As a result, the Company shifted the mine development priorities on 3 March 2023 to the 415 East ore drive. In parallel, plans commenced to bring forward LHS to begin early April to secure the short to medium term production profile at Cononish.
LHS commenced 5 April 2023 and has been progressing in line with the LHS plan. To date, 50m (2 stoping blocks) of the 115m strike length has been completed with 2,906 tonnes of ore being delivered to the ROM pad for processing since LHS began. Stoping block 2, which produced 950 tonnes of ore at an average gold grade of 11.6g/t, was above forecast grades for block 2 of 10.4g/t of gold.
As a result of the 430 West Ore drive development being halted, production for Q1 2023 (1 January to 31 March 2023) was severely impacted, totalling 758 ounces of gold for the period.
With the commencement of LHS on 5 April 2023, gold concentrate production steadily increased in Q2 2023, with a total of 1,556 ounces of gold being produced, of which 818 ounces was attributed to June 2023. For H1 2023 total gold production totalled 2,314 ounces.
Sales
Q2 2023 gold concentrate shipments totalled 269 tonnes with a sales value of
Scottish gold doré sales made to Scottish jewellery companies during H1 2023 totalled
Table 1: The following table summarises quarterly gold production and sales at Cononish on a calendar year basis:
|
Gold produced (ounces) |
Gold Sales (ounces) |
Gold sales price (£/ounce) |
Gold sales (£ million) |
2022 |
8,564 |
7,502 |
1,586 |
11.9 |
Q1 2023 |
758 |
932 |
1,622 |
1.5 |
Q2 2023 |
1,556 |
1,213 |
1,609 |
2.0 |
H1 2023 |
2,314 |
2,145 |
1,614 |
3.5 |
Mine Planning
After reconciling mine development and production over the past six months, including investigating the issues and impact of stopping the 430 West Ore drive development in late February 2023, the Company is undertaking a third-party review of the Cononish mine plan for the next twelve months.
The review will initially encompass an assessment of the mine design, schedule and production forecasts. This review will inform 2023 production forecasts and will also incorporate a second stage of power and ventilation upgrades to improve mine accessibility and enable the mine to operate all development and production equipment simultaneously to improve mine development rates. This second stage of power and ventilation upgrade allows a step change in development rates and opens up more mining fronts by enabling equipment to operate in parallel. This is necessary to complete the capital development required for ventilation, resource definition drilling and continuation of the incline to open up more mining fronts.
The Company is withdrawing its 2023 production guidance and will update the market on production forecasts and its mine plan, once the third-party review is completed, and findings have been analysed.
Processing Plant
In line with optimisation initiatives undertaken in 2022, the processing plant continues to perform in in line with expectations. Mill feed averaged 8.1g/t of gold for Q2 2023 and 6.9g/t in H1 2023. Processing plant gold recovery levels were above 94% for Q2 2023 and 94% in H1 2023. In June 2023 the processing plant processed 2,538 dry metric tonnes of ore and had 519 hours run time for the month.
An upgraded, fully automated gravity circuit is being commissioned to increase Scottish Gold doré production on site. The circuit is expected to be fully commissioned Q3 2023.
As previously announced the tailings thickener, designed to increase throughput of ore, is ready to be commissioned. The Company will commission the tailings thickener when sufficient ore is being delivered from the mine for it to be effective.
Financing
The Group held
Scotgold Resources Interim CEO, Sean Duffy said: "H1 2023 has been disappointing in terms of gold production and development of the underground mine at Cononish. The impact of the declining of gold grades in the 430 West Drive, late February was significant and evident in the resultant production figures for the period. Notwithstanding these difficulties, LHS has progressed in line with our plans and I want to thank our dedicated team for working safely and tirelessly to deliver this, with Q2 2023 production being steady and increasing as a result.
"We have begun a mine plan review following reconciling Cononish's mine development and production over the past six months. This review will allow us to recalibrate our current 2023 mine plan to best optimise LHS going forward as we continue to develop the mine with a view to achieving full production in the long-term."
**ENDS**
Scotgold Resources Limited Sean Duffy, interim CEO and CFO Peter Hetherington, Non-executive Chairman
|
Via Celicourt Communications
|
Shore Capital (Nomad and Broker) Toby Gibbs / Tom Knibbs
|
Tel +44 (0) 20 7408 4090 |
Celicourt Communications (Financial PR) Felicity Winkles
|
Tel +44 (0) 774 8843 871 |
Notes
Scotgold Resources Ltd (AIM:SGZ), is
It is Scotgold's vision to build a mid-tier gold mining company in
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.