22 October 2024
Petro Matad Limited
("Petro Matad" or the "Company")
Planned production startup at Heron-1
Petro Matad Limited (AIM: MATD), the AIM quoted Mongolian oil company, provides the following update on the planned start of oil production in its Block XX Production Sharing Contract area in eastern
Highlights
· Construction and equipment installation activities at the Heron-1 well pad have been completed and commissioning of the site is ongoing. Start of production from the well is planned on or before 25 October 2024.
· The Company will host a delegation headed by the Ministry of Industry and Mineral Resources for a production startup ceremony at site on 25 October.
· The Cooperation Agreement with PetroChina Daqing Tamsag for use of the Block XIX production facilities and export infrastructure is in near final form.
Heron-1 production startup
Site construction and equipment installation activities on the Heron-1 well pad have been completed. The beam pump, generator and storage tanks are now being commissioned and will be ready for production startup on or before 25 October 2024. Petro Matad's in-field operations team is at site and all logistical preparations are being made to be ready to start the transportation of produced fluids to PetroChina's facilities some 20 km to the north in Block XIX.
The Company will be honoured to host a delegation headed by the Ministry of Industry and Mineral Resources at a startup ceremony at the well site on 25 October. The delegation will include senior representatives of the Ministry, senior officials of industry regulator the Mineral Resources and Petroleum Authority of
The Cooperation Agreement with neighbouring operator, PetroChina Daqing Tamsag, is in near final form. It includes provision for the offloading, measurement, processing, export and sale of the Block XX production. All fees to be levied are in line with expectations and the only item remaining to be agreed is the administration fee to be paid to PetroChina. Whilst PetroChina has advised that it will likely take some time for the agreement to be signed by its Headquarters, Petro Matad, PetroChina and MRPAM have all agreed to get Block XX production operations started ahead of the operational winter shut down in late November. Production, processing and export activities continue through the winter months, so it is important to get these started in advance.
Mike Buck, CEO of Petro Matad, said:
"We have waited a long time to get the Heron-1 well into production and we are pleased to have reached this important milestone. We very much appreciate the support of the Ministry and MRPAM and the cooperation that PetroChina is providing. We are also very grateful for the hard work and enthusiasm of our dedicated team and for the patience and continued support of our shareholders."
Further operational updates will be provided in due course.
- Ends -
For further information please contact:
Petro Matad Limited |
|
|
|
|
|
Mike Buck, CEO |
+976 7014 1099 / +976 7575 1099 |
|
|
|
|
Shore Capital (Nominated Adviser and Joint Broker) |
|
|
|||
Toby Gibbs Rachel Goldstein |
+44 (0) 20 7408 4090 |
|
|
|
|
Zeus Capital Limited (Joint Broker) Simon Johnson Louisa Waddell |
+44 (0) 20 3829 5000 |
|
|
|
|
FTI Consulting (Communications Advisory Firm) |
|
|
|
|
|
Ben Brewerton Christopher Laing |
+44 (0) 20 3727 1000 |
|
|
|
|
About Petro Matad
Petro Matad is the parent company of a group focused on oil exploration, development and production in
Petro Matad Limited is incorporated in the
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.