Bluebird Merchant Ventures Ltd / EPIC: BMV.L / Market: FTSE / Sector: Mining
18 July 2024
Bluebird Merchant Ventures Ltd
('Bluebird' or 'the Company')
Transformational free carry JV model with local partners now implemented across all three high grade gold projects bringing total investment of c.
Bluebird Merchant Ventures Ltd, a gold company primarily focused on bringing historic mines back into production, is delighted to announce that it has signed a
Overview:
· Staged
· Kochang is the smaller of the Company's high grade historic mines and has a high margin production target of 12-15,000 oz Au per annum.
· Estimated initial production can be started between 6-9 months following relevant permitting with the initial plan being to process via a toll treatment agreement.
· The JV partner, which has already committed
· BMV's technical director Graeme Fulton recently visited both Gubong and Kochang and, following meetings with the local partners, is preparing a new updated development plan for both projects.
· A Scoping Study for Kochang and Gubong included a post-tax NPV of
· Bluebird now has c.
· The Company recently announced a restructuring of the Board to lower its cost base and reflect the now fully implemented free carry JV model.
Bluebird Executive director and Interim CEO Aidan Bishop said, "The signing of a
"Kochang has significant historic data and a non JORC estimate 550-700Kt grading between 5.2-6.6 g/t Au and 27.3-34.8 g/t Ag and its 2.5km strike is open at depth and laterally. Once the MTUP has been secured, the intention is to fast track the Project to production at c.12-15koz Au pa, with trial mining expected to take between 6-to-9 months via processing ore in another Korean facility, providing cash flow for all parties. Importantly, local contractors have already been contacted to provide quotations to undertake work to rehabilitate the Kochang adit to safely prepare for commercial operations. This action is supported by our local partners.
"These are exciting times for all stakeholders. We have three exciting projects, local partners and JV funding in place, defined development paths, a lean structure and a highly positive gold price environment. I look forward to regularly updating all shareholders as we develop our multi project precious metal portfolio, as we look to become a producing entity with a cumulative production target in excess of 100,000 oz Au per annum."
Details
Kochang is recognised as the easier of Bluebird's two projects in
Under the terms of the Agreement, the South Korean's will form an SPV for the investment that will facilitate Kochang's development, investing up to
The Farm-out is over three stages with milestones needed to be achieved for the grant of equity in the JV. In the first and second stages, the JV will aim to obtain the relevant permits relating to bringing Kochang back into production (such as the Mountain Temporary Use Permit 'MTUP') and once received, prepare a Development Report, which details the planned development of taking Kochang into production. In the third stage, the JV will focus on implementing the Development Report or carrying out more exploration work to further define the orebody at the Kochang Project. For instance, along the 2.5km strike length, there is 600m between the two historic mining areas that has not yet been exploited. The expenditure during Stage 2 and 3 must be sufficient to meet the minimum work commitments for the permits for the Kochang Project for that period.
The expenditure milestones by the investor giving a total of 60% of the Project are as follows:
· Stage 1 Shares:
· Stage 2 Shares:
· Stage 3 Shares:
Bluebird shall not be required to contribute to the costs of the JV/Kochang development up to the completion of Stage 3, providing the Company with a free carry to production.
The investment is contingent on the outcome of the review being conducted by the Korean Board of Audit and Inspection ('KBAI') re the application and grant of a MTUP in respect of the Kochang Project. The Korean Mining Registration Office ('MRO') has already agreed to extend the Kochang Licence until the KBAI review is complete. Following the granting of a MTUP, there is an estimated 6-to-9-month development time to mining. Technical Director Graham Fulton has recently been on the ground to review the optimal development path. As part of this, he assessed the adit rehabilitation work which would be classified as Qualifying Expenditure and ensure the extension of the permits regardless of the outcome of the KBAI review. Importantly the local partner has indicated a willingness to commence work at the Project prior to an issuance of a MTUP.
The two parties already have a working relationship having signed a
**ENDS**
For further information please visit https://bluebirdmv.com or contact:
Jonathan Morely Kirk Bluebird Merchant Ventures Ltd Email: jmk@bluebirdmv.com
Nick Emerson SI Capital Tel: 01483413500
About Bluebird
Bluebird recognised the most effective strategy to develop projects in
The Company has three JV's providing a cumulative c.
Bluebird continues to provide technical assistance to these projects, utilising its internationally experienced mining team, which has a track record of bringing gold projects into production across
Gubong, which was historically the second largest gold mine in
Kochang is an epithermal vein deposit with parallel vertical ore bodies covering 8.3 sq km that reportedly produced 110,000 oz of gold and 5.9 million oz of silver between 1961 and 1975. Consisting of a gold and silver mine, there are currently four main veins and several parallel subsidiary veins vein which have been identified, as well as a newly identified cross-cutting vein. Historic drilling indicates the veins continue to depth below the current 150m mine and mapping shows the veins on surface providing potential above and below the old workings. The veins extend to the NE providing a strike length of 2.5km with 600m between the two mines not exploited. There is potential to expand operations to the southwest/northeast and to depth, as well as exploit the already mined areas. The total resource potential is between 550,000 and 700,000 tonnes, with a range of grades between 5.2 g/t to 6.6 g/t gold, and 27.3 g/t to 34.8 g/t silver. Following the granting of a Mountain Use permit, there is an estimated 6-to-9-month development time to trial mining.
Batangas is a 1,160-hectare licence with a 25-year Mineral Production Sharing Agreement ('MPSA') granted. The Project has a current JORC compliant resource of 440,000 ounces, including a maiden ore reserve of 128,000 ounces (including silver credits) as well as multiple additional targets providing extensive resource upside. Exploration expenditure to the tune of c.
Work is focused on completing Exploration and Environmental Work Programmes initially targeting the high-grade 1,164-hectares Lobo licence. This has an initial Probable JORC Compliant Ore Reserves of 171,000 tons at 6.6 g/t for 36,000 ounces of gold excluding silver credits based primarily on the South West Breccia ('SWB') area of the licence that can be mined in the first 18 months of any operation. There is an Indicated resource of 82,000 oz Au that is perceived as easily convertible. Additionally, the area has multiple epithermal and high-grade targets already identified for resource expansion with 15km of identified mineralised structures with results across the nine identified targets yielding excellent results. These include 2.1m @14.4g/t Au and 3m at 12.1g/t at West Drift, which already has an Indicated and Inferred resource of 350,000t at 3 g/t Au, 8.35m at 18.3 g/t Au and 6.0m at 31.2 g/t Au located immediately west of the SWB Extension, 19m surface channel sample with intersections of 19m grading 9.8 g/t Au at Ulupong and trenching at Limestone Target yielded 3.5m at 25.9 g/t Au including 1.5m at 56.8 g/t Au.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.