BHP Group Limited
Exchange release
19 October 2024
Samarco Update - Brazil Settlement Negotiations
BHP notes the recent press speculation in Brazil regarding the status of negotiations in Brazil between Samarco Mineração S.A. (Samarco), BHP Billiton Brasil Ltda (BHP Brasil) and Vale S.A. (Vale) (the Companies) and the Federal Government of Brazil, State of Minas Gerais, State of Espirito Santo, public prosecutors and public defenders (Public Authorities).
The Companies are continuing to negotiate a full and final settlement of the Framework Agreement obligations, the Federal Public Prosecution Office civil claim and other claims by the Public Authorities relating to Samarco's Fundão dam failure on 5 November 2015 and are considering the terms of a settlement proposal.
The negotiations between the parties are ongoing and no final agreement has been reached on the settlement amount or terms. Any settlement is subject to finalisation of the terms and conditions of a final settlement agreement, entry into final and definitive settlement documentation by the Companies and Public Authorities and approvals by the Boards of the Companies and by the Public Authorities.
The negotiations are being conducted by the Brazilian Federal Court of the 6th region (TRF-6) and the National Council of Justice in Brazil with the oversight of a court-appointed mediator and the participation of public prosecutors and public defenders who are representing interested parties in the negotiation process.
The parties are negotiating a settlement proposal that would provide a total financial value of approximately R$170 billion1 (
The final settlement is expected to provide reparation for the impacts of the dam failure and resolve the Federal Public Prosecution Office claim and all existing claims by the Public Authorities in relation to the dam failure.
The final settlement would:
· establish a new compensation and indemnification system that was designed with the collaboration and endorsement of the public defenders and prosecutors to provide compensation for eligible people in the affected regions. Individuals and small businesses who agree to opt-in to the settlement will be compensated
· provide compensation and performance obligations to complete the community resettlements and other socioenvironmental programs, including environmental remediation; and
· provide
Summary of financial arrangements
The settlement proposal incorporates amounts already invested to date plus future payments and obligations as follows:
· R$38 billion (approximately
· R$100 billion1 (approximately
· Additional performance obligations for an estimated financial value of approximately
The Obligations to Perform will include the establishment of a new compensation and indemnification system, commitment to remove a certain amount of tailings from the Doce River subject to a licencing process, ongoing monitoring for potential environmental contamination in certain areas of the Doce River and the transition of the Renova Foundation's remaining programs to Samarco.
Financial obligations1,2
Under a final settlement agreement, Samarco would be the primary obligor for the settlement obligations and BHP Brasil and Vale are each secondary obligors of any obligation that Samarco cannot fund or perform in proportion to their shareholding at the time of the dam failure, which is 50% each.
|
|
|
Spent to date (as at 30 September 2024) (100%) |
38 |
7.9 |
Obligation to Pay (100%) |
100 |
18.0 |
Obligations to Perform (100%) |
32 |
5.8 |
Total Settlement Amount in the settlement proposal (100%) |
170 |
31.7 |
Total - BHP Brasil share (50%) |
85 |
15.9 |
The settlement proposal is broadly aligned with the existing
Under the terms of Samarco's Judicial Reorganisation Plan, Samarco's funding of remediation obligations will be capped at
Other litigation not resolved by a final settlement
A final settlement would not resolve the Australian class action complaint, United Kingdom group action complaint, the group action claim brought against certain Vale and Samarco entities in the Netherlands, criminal charges against Samarco, BHP Brasil, Vale and certain individuals, civil public actions commenced by private associations, including the civil public action concerning the use of Tanfloc for water treatment, trailing litigation from individuals (among others) and future or unknown claims which may arise from new information or damages in connection with the dam failure.
The trial for the United Kingdom group action complaint commences 21 October 2024. BHP will continue to defend the action which it believes is unnecessary because it duplicates matters already covered by the ongoing reparation work and legal proceedings in Brazil.
Authorised for release by Stefanie Wilkinson, Group General Counsel and Group Company Secretary
Contacts |
|
Media media.relations@bhp.com |
Investor Relations investor.relations@bhp.com |
Australia and Asia Josie Brophy +61 417 622 839
|
Australia and Asia John-Paul Santamaria +61 499 006 018 |
Europe, Middle East and Africa Gabrielle Notley +61 411 071 715
|
Europe, Middle East and Africa James Bell +44 7961 636 432 |
Latin America Renata Fernandez +56 9 8229 5357 |
Americas Monica Nettleton +1 (416) 518-6293 |
North America Megan Hjulfors
|
|
BHP Group Limited ABN 49 004 028 077 LEI WZE1WSENV6JSZFK0JC28 Registered in Australia Level 18, 171 Collins Street Melbourne Victoria 3000 Australia Tel: +61 1300 55 4757 Fax: +61 3 9609 3015 BHP Group is headquartered in Australia
bhp.com |
|
1 Future financial obligations are presented on a real, undiscounted basis and will accrue inflation at IPCA inflation rate. Payments will be made in Brazilian Reais.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.