16 December 2024
Rainbow Rare Earths Limited
("Rainbow" or "the Company")
LSE: RBW
Interim Economic Study confirms Phalaborwa as one of the highest margin rare earth projects in development today
· Post tax NPV10 of
· Project economics remain robust despite two years of inflation totalling ca. 12% since publication of the PEA and modifications to the flowsheet.
· Project remains resilient to the rare earth element ("REE") price cycle, with average production cost of
· The low operating cost establishes Phalaborwa as the highest margin REE project in development today outside of
· Updated up-front capital cost of
· The Interim Economic Study represents a much higher level of confidence in both the processing flowsheet prior to separation and capital and operating cost estimates than the PEA.
· Further opportunities for operating and capital cost optimisation will be explored in H1 2025 alongside separation test work.
· Additional revenue streams from the sale of other, non-magnet, REE and final gypsum residue are expected to further enhance economics, but are not included in the current study.
NEWS RELEASE
Rainbow announces the key outcomes of an updated economic analysis (the "Interim Study") carried out in H2 2024. The aim of the Interim Study was to update the economics of the project further to changes to the primary flowsheet to recover REE from the phosphogypsum stacks at Phalaborwa, as well as updating to current market pricing for all key areas of capital and operating costs.
The Interim Study, carried out in conjunction with independent consultants METC Engineering in
In addition to confirming the robust economics of Phalaborwa, the Interim Study has highlighted a number of areas for further operating and capital cost optimisation, which will be done in parallel with the ongoing rare earth separation test work.
George Bennett, CEO of Rainbow, commented: "The findings of the Interim Study confirm the exceptional economics of Phalaborwa first published in the PEA, after two years of significant inflationary pressure. The capital and operating cost estimates, now at a much higher level of economic confidence than at the PEA stage, confirm that Phalaborwa remains the highest margin rare earth project in development today outside of
This update reaffirms that Phalaborwa is extremely well positioned to contribute to the establishment of an independent and resilient supply chain for the REE critical to decarbonisation, defence and emerging technologies.
Going into the New Year, we now look forward to focusing on opportunities to drive further optimisation of our capital and operating costs, and to completing the separation test work."
Investor Meet Company Presentation - Tuesday 21 January 2025
Rainbow CEO, George Bennett, and Technical Director, Dave Dodd, will provide a live presentation via Investor Meet Company on Tuesday 21 January at 10:00 BST.
The presentation is open to all existing and potential shareholders. Questions can be submitted pre-event via your Investor Meet Company dashboard up until 20 January 2025, 09:00 BST, or at any time during the live presentation.
Investors can sign up to Investor Meet Company for free and add to meet RAINBOW RARE EARTHS LIMITED via: https://www.investormeetcompany.com/rainbow-rare-earths-limited/register-investor
Investors who already follow RAINBOW RARE EARTHS LIMITED on the Investor Meet Company platform will automatically be invited.
Interim Study findings
The Interim Study is based on a project life of 16 years (two years longer than that envisaged in the PEA due to the 15% increase in Resource tonnages announced in September 2024), processing an average of 2.2 Mt of phosphogypsum per annum. The overall recovery rate of magnet REE remains the same as that of the PEA at 65% based on the pilot campaign undertaken in 2023 to 2024, with ca. 1,900 t magnet REO production annually.
When calculated on the same basis as the PEA, this operation delivers a post-tax NPV10 of
The Interim Study operating cost is ca.
The operating cost has been impacted by ca. 34% inflation for the cost of power in
Phalaborwa's operating cost is considerably lower than traditional rare earth projects as the phosphogypsum material is already sitting at surface in a chemically cracked form, which eliminates the cost and risk of mining, hauling, crushing, grinding, flotation, and cracking. This favourable profile positions Phalaborwa as the highest margin rare earth project in development today outside of
The updated
Resilience to rare earth price cycle
Due to its low operating cost profile, Phalaborwa is notably resilient to the rare earth price cycle, which can be volatile. The chart below shows the project's robust EBITDA operating margins in various pricing scenarios, with the project still producing ca.
Notwithstanding recent price weakness, industry commentators agree that the longer-term outlook for REE pricing is supportive given the unstoppable global megatrends of the green energy transition and decarbonisation, as well as new exciting markets such as robotics and advanced air mobility which are primed for exponential growth.
Furthermore, the fraught nature of the geopolitical landscape has led to the drive from Western and aligned governments to reduce supply chain vulnerability through diversified sources of supply that are traceable and meet high ESG standards. Government investment allows for increased certainty for project development despite the current pricing environment and Rainbow's Phalaborwa project has been chosen by the
Interim Study parameters
As previously announced, the primary flowsheet developed by Rainbow has been subjected to large scale pilot test work in
The Interim Study therefore presents a much higher level of confidence in the processing flowsheet prior to separation. It has been prepared to a higher level of economic accuracy, compared to the PEA, and includes updated economics based on:
· Current market prices received from multiple vendors for all major finalised mechanical equipment and associated platework.
· Current market prices received for all key reagents and supplies, with consumption requirements confirmed for the primary flowsheet by the pilot plant test work.
· Detailed reclamation costs following successful piloting of the proposed hydraulic reclamation system.
· Geotechnical and hydrology tests completed across the whole project.
· Materials of construction studies completed for the process plant, allowing suitable grade materials to be selected and priced.
The Interim Study includes separation economics based on the original high level PEA assumptions adjusted for estimated 12% global inflation. Separation testwork has commenced at Rainbow's dedicated in-house laboratory facilities in
The team will also evaluate the economics for separation of the SEG group (samarium, europium and gadolinium), lanthanum ("La") and cerium ("Ce"). The potential revenue from these non-magnet REE is not included in the headline economics set out in the Interim Study. Rainbow also expects to generate revenue from the sale of processed phosphogypsum, which has also been excluded from the Interim Study to ensure comparability with the 2022 PEA. Rainbow will provide updates as the separation work progresses in 2025.
Market Abuse Regulation Disclosure
This announcement contains inside information for the purposes of Article 7 of the Market Abuse Regulation (EU) 596/2014 as it forms part of
For further information, please contact:
Rainbow Rare Earths Ltd |
Company |
George Bennett Pete Gardner |
+27 82 652 8526
|
|
IR |
Cathy Malins |
+44 7876 796 629 |
Berenberg |
Broker |
Matthew Armitt Jennifer Lee
|
+44 (0) 20 3207 7800 |
Stifel
|
Broker |
Ashton Clanfield Varun Talwar
|
+44 20 7710 7600 |
Tavistock Communications |
PR/IR |
Charles Vivian Tara Vivian-Neal |
+44 (0) 20 7920 3150 |
Notes to Editors:
About Rainbow:
Rainbow Rare Earths aims to be a forerunner in the establishment of an independent and ethical supply chain of the rare earth elements that are driving the green energy transition. It is doing this successfully via pioneering the first commercial recovery of rare earth elements from phosphogypsum that occurs as the by-product of phosphoric acid production. These projects eliminate the cost and risk of mining, meaning that they can be brought into production quicker and at a lower cost than traditional hard rock mining projects.
The Company is focused on the development of the Phalaborwa Project in
The Phalaborwa updated interim economic study released in December 2024 has confirmed strong base line economics for the project, which has a base case NPV10 of
More information is available at www.rainbowrareearths.com
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.