THIS ANNOUNCEMENT CONTAINS INSIDE INFORMATION FOR THE PURPOSES OF THE MARKET ABUSE REGULATION (EU) NO. 596/2014 (INCLUDING AS IT FORMS PART OF THE LAWS OF
26 April 2024
Ferro-Alloy Resources Limited
("Ferro-Alloy" or the "Group" or the "Company")
Q1 2024 Production Results
Increased Q1 production year on year
Ferro-Alloy Resources Limited (LSE:FAR), the vanadium producer and developer of the large Balasausqandiq vanadium deposit in
Q1 Production Results
|
2023 |
2024 |
|||||
|
Q1 2023 |
Q2 2023 |
Q3 2023 |
Q4 2023 |
FY 2023 |
Q1 2024 |
Q1 % change |
|
|
|
|
|
|
|
|
Tonnes of concentrate processed |
194.1 |
1,016.6 |
314.0 |
703.3 |
2,228.0 |
668.6 |
+244.5% |
|
|
|
|
|
|
|
|
Tonnes of vanadium pentoxide produced* |
31.3 |
141.4 |
47.3 |
90.5 |
310.5 |
81.6 |
+160.7% |
|
|
|
|
|
|
|
|
Tonnes of molybdenum produced** |
6.5 |
14.1 |
6.4 |
7.4 |
34.4 |
7.1 |
+9.2% |
|
|
|
|
|
|
|
|
Tonnes of nickel produced*** |
9.7 |
50.8 |
15.7 |
35.2 |
111.4 |
33.4 |
+244% |
* partly contained in ammonium metavanadate
** in ferro-molybdenum
*** in nickel concentrate
Commentary
Production in Q1 2024 was 160% higher than Q1 2023, but slightly lower than planned, impacted mainly by severe flooding in
During the quarter, several improvements were made to the production facilities, including the installation of new cyclones on two of the roasting ovens in order to increase recovery and reduce emissions. A reorganisation of the drying oven and dissociation oven was also undertaken to increase overall recoveries. Two new drying ovens are currently being installed and will be commissioned during May.
Production Outlook
The impact of the floods has also affected production at the start of April but the improvements in the plant described above, together with the expected operation of the pre-roaster, should increase production to compensate.
The Company has sufficient feedstock in its warehouse for processing over the next two months and further concentrate deliveries are expected to arrive on site to enable uninterrupted production.
The Company has also started to source and treat raw materials for processing on a tolling basis which eliminates the risk of price movements between the time of purchase of concentrates and the sale of the product.
Commenting on the production results, Nick Bridgen, CEO of Ferro-Alloy Resources said:
"The first quarter of the year always produces challenging winter weather, but we are pleased to see a solid increase on the same quarter last year despite more severe weather. We are hopeful that we will be able to build on the success of this quarter throughout the rest of the year."
For further information, visit www.ferro-alloy.com or contact:
Ferro-Alloy Resources Limited |
Nick Bridgen (CEO) / William Callewaert (CFO) |
info@ferro-alloy.com
|
Shore Capital (Joint Corporate Broker)
Liberum Capital Limited (Joint Corporate Broker) |
Toby Gibbs/Lucy Bowden
Scott Mathieson/John More
|
+44 207 408 4090
+44 20 3100 2000
|
St Brides Partners Limited (Financial PR & IR Adviser) |
Ana Ribeiro / Charlotte Page |
+44 207 236 1177 |
Notes to Editors
About Ferro-Alloy Resources Limited:
The Company's operations are all located at the Balasausqandiq deposit in Kyzylordinskoye Oblast in the South of
a) the high grade Balasausqandiq vanadium project (the "Project"); and
b) an existing vanadium concentrate processing operation (the "Existing Operation")
Balasausqandiq is a very large deposit, with vanadium as the principal product together with several by-products. Owing to the nature of the ore, the capital and operating costs of development are very much lower than for other vanadium projects.
The most recent mineral resource estimate for ore-body one (of seven) provided an Indicated Mineral Resource of 32.9 million tonnes at a mean grade of 0.62% V2O5 equating to 203,364 contained tonnes of vanadium pentoxide ("V2O5"). In the system of reserve estimation used in
The Project will be developed in two phases, Phase 1 and Phase 2, treating 1m tonnes per year and an additional 3m tonnes per year. Production will be some 5,600 tonnes of V2O5 from Phase 1, rising to 22,400 tonnes V2O5 after Phase 2 is commissioned.
There is an existing concentrate processing operation at the site of the Balasausqandiq deposit. The production facilities were originally created from a 15,000 tonnes per year pilot plant which was then expanded and adapted to recover vanadium, molybdenum and nickel from purchased concentrates.
The existing operation is located on the same site and uses some of the same infrastructure as the Project, but is a separate operation which will continue in parallel with the development and operation of the Project.
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.